Production Plan End Date

Production

Auto-compute the end of a production plan from its sequential stages.

Expression

End = Start + Σ Stage_duration_days

Inputs

Start
date
Stage_duration_days

Days per stage (Yarning, Weaving, Dyeing, Finishing, …).

Output

End
date

Worked Example

Start

2026-04-20

Stages

Yarning 5d → Weaving 7d → Dyeing 4d → Finishing 3d

Result:2026-05-09 (19 days)

Notes

  • Each stage's Start equals the previous stage's End (no gaps).
  • The elapsed bar on the PO detail page uses (now − Start) / (End − Start) × 100.